Zavorichi village. Waterproofing artificial pond
Waterproofing of an artificial pond for the storage of petroleum products.
DESCRIPTION
Our specialists carried out the installation on the territory of the new base.
HDPE geomembranes. Two fire reservoirs with a total volume of 12000m3.
Reliable, high quality, and durable.
COMPLETED PROJECTS
- Excavation works. Trench construction along the perimeter.
- Manual soil planning, mechanical compaction, base compaction.
- Laying additional protection (geotextile).
- Laying, cutting HDPE Geomembranes.
- Membrane welding spec. equipment, the formation of a double seam.
- Local welding of joints, overlaps, complex assemblies, pipes.
- Checking the tightness of the double seam with an overpressure needle.